1. Acceptance materials: The water pipes and their accessories enter the site, and the owner and the installation workers will accept them together.
2. Construction preparation: prepare electric drill, hot melt machine, tape measure, screwdriver, pipe and accessories.
3. Position positioning: According to the direction of the water pipe, the screw and the pipe clamp are in place to determine the distance between the hot and cold water pipes.
4. Drilling holes: Use an electric drill to drill holes on the positioning point. At this time, pay attention to the direction of the wires and be careful of electric shock.
5. Measure the size: Use a tape measure to measure the length of each segment. Generally speaking, the width of a wall is one
Segmented hose length.
6. Melting pipe: Put the cut water pipe and elbow on the hot melting machine, and the temperature is generally 280-300 degrees.
7. Takeover: The hot-melt water pipes are quickly joined in a few seconds, and the action is fast and agile, and the joined water
The direction of the tube should be regular.
8. Installation and fixation: Put the joined water pipes on the shelf, adjust the angle, and fix them with pipe clamps.
9. Pressure test: under the supervision of the owner, test the pressure with a pressure gauge of 10mpa, and check the pressure gauge after 1 hour.
In this case, it falls back 0.05mpa, which proves that the installation is qualified.
10. Plug the nozzle: wrap the raw material tape on the plug wire to prevent water leakage, then screw the plug to the nozzle and align.
Tighten the thread.
11. Completion acceptance: Please install the waterway diagram to check the entire water pipeline route. The overall laying should be horizontal, horizontal and vertical.
Solid and reliable. Finally, fill in the relevant documents, water route map and warranty card.