What are the key points that should be mastered in the heating and debugging of the floor heating system?

Jul 31, 2022

System thermal debugging is an important link to ensure and further assess and test the quality of engineering design and construction, and must be carried out carefully. During the trial operation, the water temperature for initial heating should be strictly controlled, and the heating process must be stable and slow to ensure that the building components have a gradual adaptation process to the temperature rise.

During initial heating, the heating temperature of the debugging hot water should be gentle, and the temperature of the water supply should be controlled at about 10°C higher than the ambient temperature at that time, and should not be higher than 32°C. °C until the design water supply temperature is reached. At this temperature, the heating pipes connected to each group of water collectors and water collectors should be adjusted one by one until the design requirements are met.