What are the requirements for laying supports for PPR water supply pipelines in the suspended ceiling

Aug 03, 2021

Cold water PP-R pipe bracket spacing

Nominal outside diameter dn 20 25 32 40 50 63 75 90 110 160

Horizontal pipe spacing (mm) 600 700 800 900 1000 1100 1200 1350 1550 1800

Riser spacing (mm) 900 1000 1100 1300 1600 1800 2000 2200 2400 2800

Spacing of hot water PP-R pipe bracket

Nominal outside diameter dn 20 25 32 40 50 63 75 90 110 160

Horizontal pipe spacing (mm) 300 350 400 500 600 700 800 1200 1300 1400

Riser spacing (mm) 400 450 520 650 780 910 1040 1560 1700 2000

The PP-R should be fixed and supported at the following locations: (1) The tee, elbow, etc. of the horizontal pipeline are easily loosened; (2) The elastic sealing ring is connected to the socket of the pipeline; (3) The displacement of the pipe is restricted; ( 4) Pipeline installation of valves and other pipeline accessories; (5) Between two expansion joints; (6) The position where the main water flow changes direction; (7) The installation of water supply accessories such as valves, water meters, and float valves.